Energy Law (“Official Gazette of RS”, No. 145/14 and 95/18 –another law), proscribes the jurisdiction of the Government, i.e. the ministry competent for energy issues in the field of renewable energy sources. Therefore, the jurisdiction of the Agency in this field is limited exclusively to:

  1. issuance and withdrawal of licence for power production and combined power and heat production from renewable energy sources.
    The licence is issued upon an energy entity’s application under the conditions prescribed by the Law for a power producing facility if the total approved power of the connection amounts to:
    • over 1MW – (power production facilities);
    • over 1 MW of total electricity and over 1 MWt total heat – (combined heat and power plants).
  2. approval of a transmission system operator’s legal document which defines the level of fee for the issuance, transfer and use of guarantee of origin
  3. monitoring system operators and suppliers in terms of their procedures related to prescribed commitments in the field of guarantees of origin

All other competences in the field of renewable energy sources, except for the ones mentioned above, are within the jurisdiction of the Government i.e. the ministry in charge of energy issues (Art. 65-66, Art. 67, Art. 70 – 87 of the Energy Law) and they include, in particular:

  • adoption of the National Action Plan which defines targets for the use of renewable energy sources;
  • more detailed definition of conditions for the award of a privileged power and heat producer status, a temporary privileged producer status and the status of a producer of power from renewable energy sources;
  • adoption of a decision on the award of the status of privileged producer and temporary privileged producer as well as more detailed definition of the content of the application and of proofs for the award of the privileged producer status;
  • keeping registry of producers who have been awarded with the status of a privileged producer, temporary privileged producer and producer using renewable energy sources;
  • definition of incentive measures for the use of renewable energy sources for power production (the so-called feed-in-tariff);
  • definition of content and procedure of issuance, transfer and termination of guarantee of origin, procedure for keeping registry of guarantees of origin, except for the fee level;
  • more detailed definition of content and duration of pre-agreement and of power purchase agreement that is signed with privileged producers;
  • definition of the procedure of calculation and paying incentive fees, as well as the procedure for the allocation of funds arising from this source;
  • adoption of a legal document regulating conditions on the issuance and withdrawal of licences in detail,
  • adoption of a legal document regulating in detail conditions for the issuance of energy permits for the construction of facilities as well as for the issuance of energy permits in line with the procedure prescribed by the Law upon applications an investor has filed with the ministry in charge of construction of facilities:
    • for power production of 1 MW and higer,
    • for combined heat and power production in combined heat and power plants with the capacity of 1MW and higher of electrical power and 1MWt and higher of heatng power.
News
APPROVAL OF RULES REGULATING PROCEDURE AND METHOD OF TRANSMISSION CAPACITY ALLOCATION BETWEEN BIDDING ZONES

BELGRADE, Friday, November 29, 2024.

On the session held on November 28, 2024, the Council of the Energy Agency of the Republic of Serbia has approved rules regulating the procedure and method of transmission capacity allocation on borders between bidding zones of the transmission system operator of the Republic of Serbia (EMS AD) and the transmission system operators of North Macedonia (MEPSO), Romania (Transelektrika), Bosnia and Herzegovina (NOSBiH), Bulgaria (ESO), Croatia (HOPS) and Montenegro (CGES) for 2025. 


APPROVAL OF NATURAL GAS DISTRIBUTION SYSTEM OPERATOR DEVELOPMENT PLAN OF “YUGOROSGAZ” JSC BELGRADE

BELGRADE, Thursday, October 17, 2024.

On the session held on October 17, 2024, the Council of the Energy Agency of the Republic of Serbia has adopted a decision on the approval of the Distribution System Development Plan for 2024-2028 with the investment plan for 2024-2026 which was submitted to the Agency by the natural gas distribution system operator “Yugorosgaz” JSC Belgrade.

The plan envisages the natural gas distribution system development in line with the customers’ connection demand.


APPROVAL OF NATURAL GAS DISTRIBUTION SYSTEM OPERATOR DEVELOPMENT PLAN OF PUBLIC UTILITY COMPANY “STANDARD”, ADA

BELGRADE, Friday, October 11, 2024.

On the session held on October 9, 2024, the Council of the Energy Agency of the Republic of Serbia has adopted a decision on the approval of the Distribution System Development Plan for 2024-2028 with the investment plan for 2024-2026 which was submitted to the Agency by the natural gas distribution system operator PUC “Standard”, Ada.


Тitle 2

Short news


CERTIFICATE OF INDEPENDENT SYSTEM OPERATOR TO TRANSPORTGAS SRBIJA NOVI SAD

BELGRADE, Thursday, July 25, 2024.

Acting upon an application of the Limited Liability Company TRANSPORGAS SRBIJA Novi Sad, on the session held on July 25, 2024, the Council of the Energy Agency of the Republic of Serbia has adopted a preliminary Decision on issuing a certificate to the TRANSPORTGAS SRBIJA Novi Sad as to an independent system operator.


Instructions for working with clients